Thursday, January 6, 2011

BUNKER PROJECT PROGRESS

We are renovating all of the green side bunkers at Deer Creek.  We start by removing all of the sand and drainage in the bunkers.  We then install new liner in the bunker.  Finally we add new drainage and sand resulting in a new sand bunker that will play awesome and drain well for years to come.
We currently have all of the green side traps excavated and liner installed.  We are now in the finishing stages of the project where we are installing the new sand.  We currently have 30% of the bunkers filled with sand.  We plan to complete the remaining 70% by Feb. 15, 2011.